- Garage door install for the fire apparatus bays continue and are nearly complete
- Interior work continues including framing, sheet rocking, plumbing, electrical, and mechanical work
- Interior painting continues
- Glass and windows are being installed
Here’s what is coming up:
- Interior work, including sheet rocking and electrical, mechanical, and plumbing will continue
- Additional glass and windows will be installed
- Exterior site work of storm sewer and concrete apron installation will be coming up in the next couple of weeks
Concrete Apron Prep
Window Installation 
Utility Installation 
Why a new building?
When the planning process started, we looked at this project as a remodel and addition to the current fire station. As we went through the structural analysis, it was determined that due to the foundation and design of the current building, parts of it would need to be demolished and then rebuilt.
Because a part of the building would need to be demolished in order for us to add on, it ended up being a similar cost to build a new building. With a new building, we also have some additional benefits:
- more efficient use of space
- long-term maintenance for new building is more cost effective reduces construction timeline